Box No. |
Box Name |
Folders |
Dates |
Dimensions |
Summary |
|
J104 |
Correspondence |
8 |
February 1978 - May 1986 |
0.12 |
press releases; publications; correspondence; time/construction schedules; zoning/building code information [phase I time schedule for development of Mamilla] |
J105 |
Correspondence, Reports, and Zoning Information |
8 |
April 1975 - July 1989 |
0.15 |
correspondence; zoning/building code information; drawings/sketches; cost estimates; reports [background material for site plan and detailed building plan for Mamilla; economic report] |
J111 |
Correspondence, Reports, and Construction Schedule |
8 |
May 1973 - November 1982 |
0.18 |
correspondence; contracts; legal approvals/permits; time/construction schedules; drawings/sketches; project design criteria/program; reports [reports, "Jaffa Gate Parking Garage Functional Design and Economic Evaluations;" economical report; stages and timetable for construction] |
J122 |
Publications |
1 |
June 1975 - February 1977 |
0.02 |
press releases; publications |
J17 |
Correspondence and Drawings |
3 |
April 1980 - February 1988 |
0.11 |
correspondence; drawings/sketches |
J72 |
Brochure and Project Design Program |
1 |
October 1972 |
0.003 |
brochures; project design criteria/program |
J73 |
Reports and Project Design Programs |
5 |
June 1972 - June 1985 |
0.13 |
brochures; zoning/building code information; drawings/sketches; project design criteria/program; reports [market development potentials for Mamilla; layout for brochure with photographs; background program for district committee] |
J74 |
Jaffa Square: Drawings and Sketches |
2 |
January 1976 - April 1981 |
0.07 |
correspondence; drawings/sketches |
J75 |
Publications and Correspondence |
5 |
July 1973 - August 1981 |
0.12 |
publications; correspondence; drawings/sketches [photocopies of assorted newspaper articles; draft of book about Mamilla; infrastructure master plan] |
J77 |
Drawings, Zoning, and Building Code Information |
5 |
June 1972 - April 1987 |
0.13 |
brochures; publications; correspondence; reference material from other projects; zoning/building code information; drawings/sketches; reports [brochure, "The Connection of the Old City with the New City;" draft for book; landscape perspectives] |
J78 |
Correspondence and Reports |
4 |
January 1973 - January 1978 |
0.15 |
publications; correspondence; project design criteria/program; reports [photocopies of assorted newspaper articles; summaries of official proceedings, proposals by various sources; "Mamilla Report"] |
J79 |
Feasibility Studies, Zoning, and Building Code Information |
5 |
July 1972 - May 1987 |
0.2 |
contracts; time/construction schedule; feasibility studies; zoning/building code information; drawings/sketches; project design criteria/program; reports ["Time Table for Implementation and Estimated Cash Flow;" "Mamilla Options and Stages of Construction Development;" description of general Mamilla program; infrastructure proposal] |
J89 |
Drawings and Project Design Program |
1 |
June 1980 - July 1980 |
0.01 |
drawings/sketches; project design criteria/program |
J92 |
Project Design Criteria and Program |
2 |
October 1975 - September 1985 |
0.12 |
publications; zoning/building code information; project design criteria/program; reports [newspaper articles; Mamilla master plan and realization; reports, "Twelve Years in Jerusalem"] |
OF1000.6 |
Archeological Gardens: Correspondence |
1 |
1980-1982 |
0.002 |
correspondence |
PF170.1 |
Correspondence, Reports, and Drawings |
20 |
February 1972 - May 1985 |
0.29 |
press releases; correspondence; site surveys; drawings/sketches; project design criteria/program; reports [proposed land uses-Mamilla project area; excerpts from Gladstone report, market development potentials; master plan and realization final draft report; proposed framework for study] |
PF170.2 |
Correspondence |
6 |
May 1974 - December 1979 |
0.17 |
press releases; correspondence; contracts; drawings/sketches; project design criteria/program; reports |
PF93 |
Correspondence |
1 |
April 1975 |
0.01 |
correspondence |